Potter’s Key Construction Update

I have received the following update from Minto Homes with respect to the Potter’s Key development.  This land is located to the west of Jackson Trails, north of Hazeldean Road, and east of Echowoods.

 

  • Tree removal – complete
  • Rock Blasting – estimated completion by May 5, 2017 (weather permitting)
  • Sewers and Road Installation – February – December 2017
  • House Construction Start – August 2017
  • Home Occupancies – starting in March 2018

 

Phasing timelines are as follows:

  • Phase 1 – North of Creek to start all this year and close in 2018
  • Phase 1 – South of the Creek about 40% to start this year and close in 2018 with remainder to occupy in 2019
  • Phase 2 – to start home construction and close in 2019

 

You can review the phasing map for construction here.