Potter’s Key Construction Update

potterskey

I would like to take a moment to share another update regarding construction of the Potter’s Key site.

 

I have been advised that work is running further behind schedule than anticipated. The new date that blasting is expected to be complete by is now Friday, April 28th.

The updated Potter’s Key construction schedule is as follows:

  • Rock Removal – January 15thApril 28th, 2017
  • Rock Crushing – April – June 30th, 2017
  • Servicing (Sewers & Roads) – February – December 2017 (entire subdivision)
  • House Construction – August 2017 to December 2019
  • First Homeowner Moved-In – March 2018

 

 

Some residents have expressed concern regarding what to do should they potentially experience damage due to blasting.

 

As it relates to process, the City regulates blasting through the Construction Specifications which speak to the pre-blast survey requirements (all structures within 75m) and the requirement for a third party blasting consultant to monitor the blasts to make sure the peak vibrations are in compliance.

 

I encourage concerned residents to send an email including photos and a description of any prospective damage to Kevin Lamer, Program Manager, Development Inspection at Kevin.Lamer@ottawa.ca with CC to me at Shad.Qadri@ottawa.ca.

 

Residents also have the option to submit a legal claim into the City if they are not pleased with the response from City staff or the developer, you can find more information regarding this process here.

 

For more information you may contact my office or visit my web site at www.shadqadri.com. You are also welcome to contact the Minto Communities Construction Manager, Jean-Michel Le Blanc at jleblanc@minto.com, 613-782-5717. In addition you can reach out to Domenic Idone as the secondary contact for Minto at didone@minto.com  or 613-786-7922.