Hydro Ottawa Stittsville Main Street Construction Update

Construction being undertaken by Hydro Ottawa on Stittsville Main Street will resume this spring enhancing reliability and productivity of their service.

All the major road crossings and concrete encased duct bank installations are complete.  The remaining sidewalk and interlock stone replacement will start again on April 12.  This work should take approximately three weeks to complete (weather permitting).  There will be some short duration lane closures for the concrete trucks during this work. Work will be done outside peak hours and the crews will follow proper road safety guidelines for this work.

In addition, Hydro Ottawa will begin to install the large trunk cables the first week of May for approximately three weeks. This should be little to no traffic flow issues for this work on Stittsville Main Street from Ravenscroft Court to Abbott Street.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s